The Council has released its updated delivery plan for Kings Heath and Moseley Places for People (LTN). We are disappointed that this scheme has been delayed yet again for another year, and have made representations that this timeline must be adhered to and brought forward if possible.
Full details can be found on the council website here and Birmingham BeHeard website here
Programme for delivery
Measures have been grouped into four packages and will be delivered over the next couple of years as follows:
- Package 1: improvements to phase 1 measures (to the west of the High Street) including the York Road pedestrian zone – to be delivered July to October 2025
- Package 2: measures being introduced as part of phase 2 (to the east of the High Street) including new modal filters, one-way streets, and traffic calming – to be delivered July to November 2025
- Package 3: 20mph speed limit across the project area, including all ‘boundary’ roads and measures on Coldbath Road – to be delivered February to March 2026
- Package 4: a bus gate on Addison Road and reinstate the right turn from Vicarage Road onto A435 Alcester Road – to be delivered April to June 2026
This timeline is based on the current programme but is subject to change in line with any governance and spend control processes in place.
Elements on all packages are also subject to statutory consultation on Traffic Regulation Orders, to take place before construction.